BSR's current guidance (updated 1 April 2026) defines the outcome precisely: where an application is Approved with Requirements, building work can start as planned on the parts of the application approved by BSR — but you must not start building work on any parts subject to a requirement until BSR is satisfied the requirement has been met.
Examples of requirements given in the guidance include BSR telling you to:
The CLC industry guidance discusses the premise: where it is not reasonably practicable to provide all design details at Gateway 2, BSR may grant Approval with Requirements and agree a schedule of when further details must be submitted and approved.
The approved requirements schedule is effectively a second, post-approval application programme. Discipline that works:
| Control | What it prevents |
|---|---|
| Requirement register — one row per requirement: reference, linked construction stage, responsible party, evidence to be produced, status. | Drift: requirements outliving the stage that needed them. |
| Stage-gating — the programme marks each gated work package as unstartable until BSR confirms satisfaction. | Starting work on a requirement part before it is satisfied — a compliance breach, not just a process slip. |
| Submission quality bar — each requirement response is checked to the same standard as the original application (consistency, document control, cross-references). | Responses that introduce new inconsistencies and trigger further rounds. |
| Golden thread updates — satisfied requirements update the controlled record immediately. | A handover record that doesn't match what was actually approved. |
Staged applications — permitted for single and multiple tower projects — let a project progress in separate stages, with detailed plans submitted for each stage before work on that stage may begin. BSR reviews staged applications case by case, advises contacting it before submitting staged applications for multiple tower projects, and added more detailed staged-application guidance in December 2025. Requirements can sit inside stages; the same rule applies throughout: no work on a stage or a requirement-gated part until approved or satisfied.
The CLC guidance suite published in late 2025 includes a dedicated guidance note on the approach to and management of Approval with Requirements (GN03) — worth reading alongside BSR's outcome guidance before relying on AWR as a programme strategy.
Yes — on the approved parts. Work on any part subject to a requirement must wait until BSR is satisfied the requirement is met.
No — it is an approval, and BSR's statistics track approvals-with-requirements within approval figures. But it conditions the programme: the gated parts cannot proceed until their requirements are satisfied.
Against the schedule agreed with BSR at approval. Requirements that drift past the construction stages needing them are a programme failure, not a regulatory convenience.
Decision letters include how to request a review; if still dissatisfied, appeal lies to the First-tier Tribunal.
Needs should be raised with BSR promptly. Once the approval exists, changes to the project engage the change control regime (notifiable and major changes), so variations need careful classification.
Ask about a document readiness review against an agreed scope. Customer intake opens after service qualification and an accepted engagement. Gate Zero does not provide BSR approval or design certification. Please do not attach submission documents to your enquiry.
Discuss a readiness review →This article is general guidance and not legal or building-control advice. Regulatory references reflect the position at 13 September 2026.